Monday, November 26, 2007

 
Community
Contact

Brett Harrell
Executive Director

Evermore CID
2463 Heritage Village
Suite 106
Snellville, GA 30078

(770) 979-5800
Fax (770) 979-0712
Cell (404) 966-5804

bharrell@evermorecid.org


Evermore CID Logos

Download here

 
 
Questions from the Community
The Evermore CID appreciates the broad community support

Homeowners in the areas surrounding the Highway 78 project have posed several good questions about the progress of the construction. We will attempt to provide answers and updates to your inquires here.

Why are there daytime lane closures, we understood work was to be performed at night?

The majority of road construction will take place after 7 p.m. and before 5 a.m. There will be an occasional daytime lane closure. The current lane closures, single lane for short distances, are related to utility and clearing work and these lane closures typically begin at 9 a.m. and end by 3 p.m. in an attempt to avoid rush hour.

Why are they cutting the trees on West Park Place in front of Best Buy and on the other side by the old Kroger and Outback?

Clearing on most of the approach streets to the major intersections is necessary for several reasons:

  1. Installation of new fiber optic cable to synchronize the lights -- this intersection in particular in synchronizing the light at EPP and 78 with the light at RBR and Sharp Trail.
  2. Relocation of various utilities that may include power poles as well as underground such as gas and water lines.
  3. The approach streets will also get new pavement for varying distances away from U.S. 78 to allow for a smooth transition to the new alignment of U.S. 78 once that construction is complete.
  4. The curbing in some locations is being relocated to improve the turn radius onto U.S. 78 as well as in and out of businesses. 
  5. Installation of sidewalk and sidewalk connections to existing sidewalks require clearing at some locations on side streets.

What are they clearing for behind Blockbuster, Taco Bell, and Old Cub Foods?

Nothing. They are using this area to accumulate the debris from road construction including landscaping. At some point, they will bring in a chipper and grind up all the debris for mulch to recycle.

Is there a time table for the Davis Road Connector to be completed?

Not yet. The preliminary concept meeting with GDOT was positive, but there are no final plans yet. Once final plans are completed, will take months, then we have to go through an environmental review process that may take up to 18 months, then and only then, could we begin acquisition of ROW (right of way), and then after that, schedule construction. I would guess at a minimum two to three years. If possible to accelerate, we'd like to do that, but so far, doesn't look like it.

Can you give me a general statement about the median project? The first phase is from where to where? When is this first phase expected to be completed? Lanes closing when?

Preparations for actual road construction are well underway. The clearing crews are running ahead of schedule and have already passed Parkwood Road. The clearing will include the entire 7-mile corridor at once. This includes the removal of landscaping, signs, light posts, and any other impediment that will interfere with actual road construction and/or the relocation of utilities or installation of sidewalks.

Once road construction begins, most likely the first of November, it will be in stages. The first stage is from EPP to Stone Drive. The second stage is from Stone to Killian Hill. The third from Killian Hill to Highpoint and the fourth, and final stage, is from Highpoint to SR 124. The contractor is permitted to work within two stages at a time.

Within each stage there are three phases. The first phase is on the south side of U.S. 78 and the contractor will make all the various improvements to lanes, curbs, etc. working from west to east. The second phase within each stage is the north side of U.S. 78 where the contractor will work from east to west doing the same type work on that side of U.S. 78. The final phase in each stage is the actual median construction in the center of the roadway.

Once road work begins, the contractor will re-stripe the lanes within the construction zone to have three permanent lanes heading west to Atlanta and two permanent lanes headed east to Snellville. The reversible lane lights will be fixed so as not to change within the work zone and will continue to operate as normal outside the work zone. Once the final phase, median construction, is completed in each stage, the newly created three lanes in each direction will be open to traffic prior to the contractor moving into the next stage of construction.

Each stage should take approximately 6 months - give or take. The total project must be completed by November 2009.

Lane closures vary by activity and change frequently. The best way to stay informed about lane closures is to subscribe to the Traffic Info email at the Evermore website [ http://www.evermorecid.org ] and check the site frequently for the most up-to-date info [sometimes changes during the day]. Within about two months, we will also have up and running our construction communication system on U.S. 78 that will include changeable message boards and highway advisory radio for more frequent updates. The Georgia DOT also has a telephone traffic info line. Just dial 511 and follow the prompts to get info on U.S. 78 construction, accidents, lane closures, etc.

Once active road work begins, the majority of that work will be done after 7 p.m. and before 5 a.m.

Thanks for sharing this info with the community. Please feel free to provide my info to anyone with questions and encourage them to contact me.


   

P.O. Box 412, 2463 Heritage Village, Suite 106, Snellville, GA 30078
 [O] 770.979.5800  |  [F] 770.979.0712  | 
Brett Harrell Executive Director

© Copyright 2003-2008,
Evermore Community Improvement District
 All rights reserved.